Rheinmetall UK serves as a primary defence contractor in the UK, delivering advanced land, electronics, and weapon systems to the British Army, with a strong focus on sovereign capability and local manufacturing. Key programs include the Boxer Mechanised Infantry Vehicle (MIV), the Challenger 3 Main Battle Tank, and the new "UK Gun Hall" for barrel manufacturing
In previous vehicle development programmes, ducting for systems like the Crew Temperature Control System were designed using flexible tubing connecting junction boxes fabricated from sheet metal. This approach has worked well for many years and offers a simple and affordable solution to vehicle ducting. In vehicle upgrade programmes like Rheinmetall UK’s Challenger 3 programme, this approach is no longer viable due to the significant space constraints and adaptation of the existing vehicle architecture.
A variety of production methods for complex ducting components could be used such as injection moulding or rotational moulding. These however require costly tooling and for low volume production, this tooling cost is significant. Furthermore, in vehicle development programmes, air ducting tends to go through many iterations and often requires late changes due to other subsystems competing for space. There is therefore a risk that tooling may need to be re-manufactured, and parts originally produced in time for trials have to be remade for the vehicle production run.
With these pressures in mind, additive manufacturing offers a solution. There are no tooling costs for parts, the designs can be changed rapidly to accommodate other system changes and part complexity doesn’t add cost.
SLS and SLA were both investigated in detail for this application with the decision to select FFF being multifaceted.
To reach a decision, we had to consider the pros and cons of each technology and whether we would bring it in-house or contract to supply.
The advantages of contracting production, such as no capital expenditure and accessing supplier knowhow, were outmatched by the lack of qualifying suppliers available e.g. holding Cyber Essentials + accreditation, the lower level of production control, the lower pace of learning and slower iterations by not having access to the machinery.
Both SLA and SLS demand higher capital expenditure and more challenging integration onto the shop floor.
SLS couldn’t offer a suitable material choice that met all of the requirements and with enough confidence to outweigh the greater production process complexity.
The UK supply chain for SLS parts in PA2241FR at the time was not competitive. For in-house adoption, the process was too expensive and we wouldn’t use the machine to capacity on these parts alone. If we had much higher volume requirements then SLS production in-house may have been more cost competitive.
The capital cost for FFF was substantially lower than the other options, with installation into the factory floor being far easier, fewer safety hazards and lower training requirements to be met. Rheinmetall UK had lots of experience of using FFF for producing prototypes as a design aid. This knowhow meant that adopting FFF for end use part production also presented less of a cultural and training challenge.
FFF's productivity matched the required production capacity that Rheinmetall UK needed within the Challenger 3 programme and demanded minimal shop floor space.
The weaknesses of FFF within this application can be affordably mitigated. By using vibratory tumbling and painting of the FFF ULTEM 9085 parts, a good quality of product can be made without adding significant capital and piece part cost.
Considering all these trades together. It was decided that for the production of ducting, Rheinmetall UK should pursue a strategy of manufacturing the parts in house using FFF with ULTEM 9085 since this offered the most affordable, most flexible and lowest risk solution vs. the other solutions explored.
There are a good selection of manufacturers around the globe offering high temperature FFF printers able to produce parts in ULTEM 9085. During our down selection process, we considered several manufacturers offerings.
In the end, the decision to purchase a miniFactory Ignite boiled down to:


Purchasing and installing the machine was only the first step to developing and optimising the production capability.
By having a machine on the factory floor, our designers were able to learn about the impacts of their design decisions and could quickly make changes to enhancing functionality as well as cost efficiency. We were also able to optimise the printing profiles to get the best results.
The convention for AM optimisation is normally to consolidate parts. We discovered that for this application, the opposite was true. By splitting parts and creating joints, we could reduce the amount of support material needed or even eliminate it all together. This meant that we could print parts faster with less material and less post processing labour hours. It also enabled us to reach our productivity requirements on the one machine providing significant savings.
We were able to optimise our batch layouts and establish the most cost-effective post processing approach for the given application.
Having access to the machinery also made it far easier to experiment with solutions e.g. the optimum jointing method, compatible adhesives, part numbering approaches, surface finishing methods and paint finishes. Developing this bespoke solution in the supply chain would have been time consuming and expensive.

Following the acquisition of the miniFactory Ignite machine and the work undertaken to develop the production processes, Additive Manufacturing is now the baseline solution for ducting manufacture in the Challenger 3 programme.
The adoption of additive manufacturing has enabled rapid design iteration previously unimagined. We have been able to demonstrate making design changes and producing a replacement part in day.
The change to additive manufacturing has provided large overall cost savings but the biggest benefit is in cash flow savings. By manufacturing on demand, the cost of procuring parts and placing them in stores has been mitigated. There are no tooling cost and no risk of significant increase in costs due to design changes.
With production on demand, there’s no risk of parts being lost or broken in storage and if parts to get damaged during fitting, then replacements can be quickly made.
Having the machinery on site has greatly accelerated learning. Our ‘Design for Additive Manufacturing’ skills have been improved giving better quality products, enhanced productivity and lower costs.
The adoption of additive manufacturing has also lowered programme risk overall despite being a new manufacturing process. The ability to respond rapidly to change minimises the potential for programme delays and lengthy procurement cycles.
Finally adopting Additive Manufacturing for end use parts has emphasised thinking about design optimisation and cost efficiency in manufacturing. Having the manufacturing equipment accessible to the designers has helped greatly.
This project has further accelerated Rheinmetall UK’s adoption of Additive Manufacturing for end use parts. For example, since adopting the miniFactory for manufacture of polymer ducting, the company have since invested in Rapidia’s Metal Paste Deposition technology to produce steel vehicle components. It’s likely that in the future, even more components will become cost competitive to produce with Additive Manufacturing.
By Julian Wright, Technology Programmes Manager - Rheinmetall BAE Systems Land Ltd
Header image: Challenger 3 main battle tank, Ministry of Defence © Crown copyright 2026. Used under the MOD News Licence.
"*" indica campos obrigatórios